Project: Gold's Gym Thornton

30k SF Fitness Facility     |    Thornton, Colorado     |     2024

CLIENT

Gold’s Gym

MARKET

Fitness

LOCATIONS

Thornton, CO

AVG SIZE

30,000 SF

DELIVERY

General Contractor

Executive Summary

Delivering a Full-Scale Fitness Facility Built for Performance

KLM Construction served as General Contractor for the 30,000-square-foot buildout of Gold’s Gym Thornton in Colorado.

This tenant improvement project transformed the space into a full-service fitness facility featuring locker rooms, posing rooms, saunas, turf training areas, and expansive cardio and weightlifting zones.

As part of a larger brand portfolio, the facility required strict adherence to franchise standards and disciplined execution within a multi-tenant building environment.

This case study demonstrates KLM’s ability to execute complex, occupied renovations at scale.

Project Scope

Large-Scale Fitness Buildout

  • Selective demolition
  • Framing and drywall
  • MEP coordination
  • Locker room construction
  • Sauna installation
  • Turf training area buildout
  • Gym equipment coordination
  • Specialty finishes
  • ADA compliance integration
  • Utility coordination
  • Final inspections and closeout

This was a complete 30,000 SF conversion tailored to high-performance training and operational durability.

The Challenge

Construction Above an Occupied Tenant with Hard Deadlines

Key constraints included:

  • Six-month fixed schedule
  • Construction in a building with an occupied tenant below
  • Strict franchise brand standards
  • Utility coordination requiring gas line upsizing

While the gym space itself was unoccupied, the active business below required careful planning to avoid disruption.

Upsizing the gas line required ongoing coordination with local utility providers, adding complexity to scheduling.

Phasing & Delivery

On-Schedule Completion Within Six Months

Original Schedule: 6 Months

Actual Duration: 6 Months

Delivery Method: Tenant Improvement

The project was delivered on schedule and prepared for full operational launch without delay.

KLM's Approach

Structured Coordination & Franchise-Level Execution

To ensure predictable delivery, KLM implemented:

Weekly Owner–Architect–Contractor Meetings
Maintained full alignment among stakeholders.

Utility Coordination Strategy
Maintained constant communication with local utility companies to ensure timely gas line upgrades.

Proactive Procurement
Materials were ordered early to avoid schedule impacts.

Quality Control Oversight
Ongoing system checks ensured installations met franchise standards and operational requirements.

Franchise Compliance Execution
100% adherence to Gold’s Gym brand and operational specifications.

This disciplined coordination allowed KLM to maintain schedule integrity despite external utility challenges.

RESULT

SCHEDULE PERFORMANCE

100% On-Time Delivery

FRANCHISE COMPLIANCE

100% Standard Adherence

DELIVERY METHOD

General Contractor

CLIENT OUTCOME

Repeat Work – Arvada Location Awarded